Implementation Timeline
Our implementation timelines consists of three distinct phases.
Phase 1
(Approximately 12 months to complete)
Phase 1 is deployment of degree audit and transfer articulation functionality:
- Installation
- Configuration
- User acceptance testing
- Production migration
Phase 2
(Approximately 6-12 months to complete)
Phase 2 is deployment of academic planning functionality (including Schedmule)
Stabilization
(Approximately 4-8 weeks)
After production migration of each phase, a stabilization period of 4-8 week occurs, during which the install is monitored and project teams correct any issues that may arise.
- Stabilization for Phase 1 is approximately 4 weeks
- Stabilization for Phase 2 is approximately 4-8 weeks